Progress on The PorchA view from the Grill |
Day 1, September 7, 2005 |
about 0900 CDT
|
about 1000 CDT |
about 1100 CDT
That's Dave and "Bert" doing the work |
About 3 PM as work continues. Note that the old door
is gone and the new wall frame is in place
|
At 5PM. The new door has been framed in and some
of the new lower wall is in place
|
6PM and work is done for the day.
|
Day 2, September 8, 2005 |
about 0900. Note the extra support beam below the old beam on the ceiling. | about 1200. Note the additional support at the corner near the door and the beginnings of framing out the windows. | about 1500. Work continues on window frame-out on two sices |
about 1800. Many of the exterior walls have been covered with initial panel layerment. |
Day 3, September 9, 2005 |
about 0900. We get ready to leave for the day and Dave and "Bert" measure for their work | next morning. We got back after dark and saw this when we looked on the morning of Sept 10. It takes two views to show what was done. | The new supports on the upper level (left in view) are hard to see, but the lack of screen is quite noticeable |
Due to weather no work was done on September 12, 2005 |
Day 4, September 13, 2005 |
about 0900. Work has begun on the cutting of the supports on the right. Note that the board has been moved to the right. | about 1400. All the supports on the lake facing have been installed and the old ones removed. And the board has been removed. | about 1400. Note that the sides are very open. Dave and Bert are removing a hanging piece of screen that they missed. |
about 1700. the supports on the SouthWest side have been set in. |
Day 5, September 14, 2005: |
about 1000. No visible work from this angle. | about 1400. Note that the spars have been installed on both levels of the lake-facing side and work has begun on the SouthWest side. | about 1700. Final checks. Note the lower spars have been installed. |
Day 6, September 15, 2005: |
The crew at P&M works 4 10-hour days each week (Monday to Thursday). This gives their crews a "long" weekend most weeks. | ||
about 1100. Bert and Dave work on the rubber "roofing" for the floor protection | about 1700. Note the "scuppers" cut into the lake facing so that water can flow off the rubber flooring. | |
Due to weather no work was done on September 19, 2005 |
Come back for more as the days move on.
Back to Main House Construction Page